SSI test


RMP: RMP Home | Program Information | Publications | RMP Data

 
Regional Monitoring Program 1997 Annual Report
Chapter 2.
Table 2.2.
go back
Table 2.2.
Recommendations in the Five-Year Review report that suggest specific studies or activities to be undertaken by the RMP. Recommendations that overlap with those in other chapters are cross referenced.
Recommendation Cross- Listing Responsible Parties Implementation Approach Financial Impact

2a Integrate other data for holistic appraisal 2b, 3d, 4c, 7b, 7c SFEI; RB; RMP Subs Develop study plan/work plan by RMP workgroup; new subcontract or increased effort by SFEI. substantial
2b Assess sources; develop mass balance inventory 2a, 3c SFEI; RB Develop work plan by RMP workgroup; subcontract or increased effort by SFEI. substantial
2c Define impacts on re- sources and beneficial uses SFEI; Steering Committee; RB. Develop work plan by RMP workgroup; increased effort by SFEI, RB, and SC. substantial

3g Use TSS measurements to define exceedances SFEI; Subs Develop study plan/work plan by RMP workgroup; new subcontract or increased effort by SFEI. substantial
3I Test seasonality of RMP data SFEI; Subs Develop study plan/work plan by RMP workgroup; increased effort by SFEI and subcontractors. substantial
3j Determine rates of particle burial 2.b SFEI; Subs Develop work plan by RMP workgroup; subcontract or increased effort by SFEI. substantial
 
San Francisco Estuary Institute